LTG Infra Launches New Tender to Complete Construction of the Rail Baltica Bridge over the Neris River

LTG Group’s infrastructure company, LTG Infra, has launched a new public procurement procedure for the completion of construction works on the Rail Baltica bridge over the Neris River. The new contractor will be tasked with completing the future largest railway bridge in the Baltic States, a significant portion of which has already been constructed.
The new tender follows the termination of the contract with previous general contractor Rizzani de Eccher earlier this year. The decision was made after assessing the contractor’s financial situation, progress of works and fulfilment of contractual obligations, including unsuccessful settlements with subcontractors.
“Every kilometre of Rail Baltica strengthens Lithuania’s and the entire Baltic region’s security and connectivity with Europe. Our priority is therefore to restart construction of the Neris bridge as quickly as possible and ensure that works are not halted for longer than necessary,” says Minister of Transport and Communications Juras Taminskas.
LTG Infra conducted a market consultation with potential contractors ahead of launching the tender. During the consultation, project-specific circumstances were discussed, enabling procurement documentation to be adapted to the current situation and supporting the efficient implementation of the procurement process. Technical working documentation was also updated, as the tender covers only the remaining construction works rather than the entire bridge project.
Following the contract termination, LTG Infra took over the construction site, carried out a full inventory and thoroughly documented the bridge’s actual condition. This will allow the new contractor to assume responsibility for the works smoothly and efficiently.
The Neris bridge is one of the most complex engineering structures within the Rail Baltica project in Lithuania. At 1.51 km in length, it will become the longest railway bridge in the Baltic States. Due to environmental requirements in the protected Natura 2000 area, the bridge has been designed without supports in the Neris River and requires the application of complex engineering solutions during construction.
To date, 376 piles have been installed, 11 support columns have been concreted, bridge deck construction has commenced, and approximately half of the total construction work required for the bridge have already been completed.
According to Mindaugas Ivanavičius, Rail Baltica in Lithuania Director, the decision to terminate the previous contract was necessary to protect the project schedule and ensure continuity of works.
“Having assessed all available alternatives, terminating the contract with the previous contractor was the solution that best protected the public interest and helped avoid even greater delays in the future. Our objective remains to complete the Neris bridge in parallel with embankment and railway infrastructure works currently underway in adjacent sections,” says Ivanavičius.
The first bids are expected at the beginning of 2027, followed by negotiations and submission of final offers. Construction works are planned to resume after the contract is signed.
Rail Baltica is a strategic project for the LTG Group, Lithuania, and the European Union, and it is the largest railway infrastructure project in the history of the Baltic States. Once completed, it will deliver an electrified European standard gauge railway line connecting Lithuania, Latvia, and Estonia with Central and Western Europe, strengthening regional integration, civil and military mobility, and the overall resilience of the transport system.